![]() |
Daily Tenders™ - Leads 2 Business™ Call us on +27(0)860 836 337 |
|
| 06 January 2009 | ||
Delays and Extensions of Time Time is an integral part of every construction plan and can affect each party's contractual obligations. The contractor has the right to dictate the methods and sequence used to achieve the results required by the contract; therefore, the contractor must zealously guard the time needed to complete the work. Regardless of who causes the problems, disruptions can wound and sometimes kill a project.
Be careful of the sophistication of the customer. Some years ago I was modifying a Yellow Freight facility in Milpitas, California. The work included a face-lift and modifications to the exterior of the facility. We good-naturedly signed their contract and set out to start the work. As soon as we started it rained and rained and rained. It was a sixty-day contract and it rained solid for the first three weeks. We finally were able to start and, as a good contractor, I had sent a delay letter requesting additional time. I was surprised to receive a stern letter informing me that rain in February in Northern California did not constitute abnormal weather and my request was denied. Luckily this request was a "just in case" submittal and was not needed, but I learned an important lesson. The next season we were to start a new building also in Northern California. The start date was January and there were nine months to complete it. Again it rained as it did before. This time I started early and clipped every newspaper article I could that had the words "abnormal weather." It rained for so long and so hard that the ground did not dry out enough to work on until May. We attempted to start in March, but only after the owner agreed to take financial responsibility for any failed attempts. The owner balked at one point about the delay, but the newspaper clippings clearly showed it was abnormal weather and the delay was excusable according to the contract. Typical compensable delays occur when the owner or one of the representatives, including the engineer, architect, or construction manager, has delayed the contractor in the prosecution of their work. Examples of compensable delays by the owner are
All rights reserved. |
|||