PRO FORMA APPENDIX

Clause
Special Conditions ...........................................................    1(1)(t)    *Nil/See Special Conditions of Contract
Address of Employer .......................................................    1(2)(b)   
......................................................................................
                                                                                                                  ......................................................................................
Address and telephone number of Engineer ................  1(2)(b)      .....................................................................................
                                                                                                                  ......................................................................................
Address and telephone number of Contractor ............    1(2)(b)    **..................................................................................
                                                                                                                  ......................................................................................
Amount of Suretyship : ...................................................          10    R ...................................................................................
Time within which Surety to be provided .....................          10    ......................... days from the Commencement Date
Duration of Suretyship ....................................................          10    Until issue of Certificate of Completion
Time within which Works to be commenced ...............      12(1)    ......................... days after the Commencement Date
Programme to be furnished within .................................      15(2)    ............... days after receipt of Letter of Acceptance
Special Risks insurance ...................................................  38(1)(b)    *Required/Not required
If required, to be arranged by .......................................... 38(1)(b)    *Contractor/Employer
Amount of Special Risks insurance ...............................  38(1)(b)    R ................................................................................
Minimum amount of Liability Insurance .......................  38(1)(c)    R ................................................................................
Daywork allowances ......................................................... 40(4)(b)    ....................... per cent on the gross remuneration of
                                                                                                                  the workmen and foremen actually engaged
                                                                                                                  ............................... per cent on net cost of materials
                                                                                                                  actually used
Special non-working days ...............................................          41    §The period 16 December to 5 January inclusive
                                                                                                                  plus ............................................................................
Time for Completion ..........................................................      45(1)    ð ....................................................................weeks
Amount of penalty ............................................................      46(1)    R ...................................................... per calendar day
Percentage advance on material not yet
built into the Permanent Works ....................................... 52(1)(e)    ...................................................................... per cent
Percentage retention .........................................................      52(3)
  ...................................................................... per cent
Limit of retention money ...................................................      52(3)    R ................................................................................
Retention Money Guarantee ............................................      52(6)  *Permitted/not permitted
Delivery of Contractor's final statement .........................      52(9)    Within ......... days after certified date of completion
                                                                                                                  of Works
Defects Liability Period .....................................................      56(1)    ..................................................................... months
Settlement of disputes to be by reference to 61(3)/61(4)                *Arbitration/Court  
                    .                    
Contract Price Adjustment Schedule
Coefficients for calculating Contract Price Adjustment Factor
x= ................................. a= .................................... b= .................................... c= .................................... d= .................................

"F" shall be the weighted average of the fuel indices for "Diesel, before deduction of refund" and "Diesel, after deduction
of refund" for the Coast/Witwatersrand*, weighted in a ratio of ...................... to .....................

Price variation of special materials : See Clause 49(3)**

Special materials items or                                    Method by which                                    Rate or price for
portions of the Works concerned                      variations shall be determined                the base month
..........................................................                        .........................................................          ......................................................
..........................................................                        .........................................................          ......................................................

Period of va1idity of tender ....................          .............. days from closing date for submission of tenders

                                                                                                                Signature ......................................................................
Date ........................................................                                              On behalf of .................................................................
                                                                                                                .........................................................................................

Notes:  * Engineer to delete whichever is not applicab1e.
              ** Tenderer to enter relevant information and data.
              ð If time for completion is not stipulated, Tenderer is to do so.
              § Engineer to list special non-working days.
              All other information required in the Appendix is to be entered by the Engineer.
              If Special Risks Insurance is to be provided by the Contractor, an item should be included in
              the Schedule of Quantities to cover the cost of such insurance.