Daily Tenders - Leads 2 Business Dedication to Safe Elevation Daily Tenders™ -
Leads
2 Business™

Call us on
+27(0)860 836 337

PRO FORMA

APPENDIX


Special Conditions ....................................................................
Address of Employer ................................................................

Address and telephone number of Engineer ........................

Address and telephone number of Contractor .....................

Amount of Suretyship : ...........................................................
Time within which Surety to be provided ............................
Duration of Suretyship ............................................................
Time within which Works to be commenced ........................
Programme to be furnished within .........................................
Special Risks insurance ...........................................................
If required, to be arranged by .................................................
Amount of Special Risks insurance .......................................
Minimum amount of Liability Insurance ...............................
Daywork allowances ................................................................



Special non-working days ..................................................

Time for Completion ..........................................................
Amount of penalty .............................................................
Percentage advance on material not yet
built into the Permanent Works .........................................
Percentage retention ...........................................................
Limit of retention money ...................................................
Retention Money Guarantee ..............................................
Delivery of Contractors final statement ............................

Defects Liability Period .....................................................
Settlement of disputes to be by reference to 61(3)/61(4)

Clause
 1(1)(t)
1(2)(b)

1(2)(b)

1(2)(b)

10
10
10
12(1)
15(2)
38(1)(b)
38(1)(b)
38(1)(b)
38(1)(c)
40(4)(b)



41

45(1)
46(1)

52(1)(e)
52(3)
52(3)
52(6)
52(9)

56(1)

 
*Nil/See Special Conditions of Contract
......................................................................................
......................................................................................
......................................................................................
......................................................................................

**..................................................................................
......................................................................................
R ................................................................................... 
......................... days from the Commencement Date
Until issue of Certificate of Completion
......................... days after the Commencement Date
............... days after receipt of Letter of Acceptance
*Required/Not required
*Contractor/Employer
R ................................................................................
R ................................................................................
....................... per cent on the gross remuneration of
the workmen and foremen actually engaged
............................... per cent on net cost of materials
actually used
§The period 16 December to 5 January inclusive
plus ............................................................................
ð .................................................................... weeks
R ...................................................... per calendar day

...................................................................... per cent
...................................................................... per cent
R ................................................................................
*Permitted/not permitted
Within ......... days after certified date of completion
of Works
..................................................................... months
*Arbitration/Court

Contract Price Adjustment Schedule
Coefficients for calculating Contract Price Adjustment Factor
x= ..................................... a= ........................................ b= ........................................ c= ........................................ d= .....................................

"F" shall be the weighted average of the fuel indices for "Diesel, before deduction of refund" and "Diesel, after deduction
of refund" for the Coast/Witwatersrand*, weighted in a ratio of ...................... to .....................

Price variation of special materials : See Clause 49(3)**

Special materials items or                                                Method by which                                          Rate or price for
portions of the Works concerned                                 variations shall be determined                      the base month
..........................................................                                   .........................................................                 ......................................................
..........................................................                                   .........................................................                 ......................................................

Period of va1idity of tender ....................         .............. days from closing date for submission of tenders

                                                                                                                                               Signature ......................................................................
Date ........................................................                                                                              On behalf of .................................................................
                                                                                                                                               .........................................................................................

Notes: * Engineer to delete whichever is not applicab1e.
** Tenderer to enter relevant information and data.
ð If time for completion is not stipulated, Tenderer is to do so.
§ Engineer to list special non-working days.
All other information required in the Appendix is to be entered by the Engineer.
If Special Risks Insurance is to be provided by the Contractor, an item should be included in
the Schedule of Quantities to cover the cost of such insurance.


© Copyright 1990 by the South African Institution of Civil Engineering. ® All rights reserved